City Heights Square construction remains on schedule. Concrete on the podium level (first story above ground level) at the northwest quadrant of the project will be poured on November 19.

The current major activities are rough framing, electrical and plumbing, which will continue for several more months. The next major activity will be constructing the exterior skin (ground floor storefront, stucco, brick, and board) and roofing.